Inspections Required
Request an Inspection
Call our 24-hour inspection request line at 972.291.5100 x 1093 or send an email to cityinspections@cedarhilltx.com.
Requests must be made by 6:30 a.m. for same day inspection.
Overview
- Electric Temporary Pole
- Building plans must be on site at all times
- Pier Inspection (Lakeridge) – Form board survey must be in office prior to inspection
- Plumbing Rough in – Form board survey must in office prior to inspection
- Foundation (prior to pouring) – Termite treatment report must be in office
- Second Inspection (see below)
- Insulation – Energy compliance received through third party inspection
- Fire box (If masonry)
- Sidewalk and Approach
- Building Final (see below)
Second Inspection
- Framing
- Plumbing
- Top out
- Electric rough
- Duct rough
- Brick tie
- Poly-seal
Building Final
- Building
- Plumbing
- Electric
- Heating and Air
- Final Grade (Lake Ridge Subdivision requires submittal of precise lot grading plan prepared by a land surveyor)
- Termit Treatment Certification must be in office prior to inspection
- SIC Letter must be in office prior to inspection
- IECC Compliance Letter from a third party inspector must be in office prior to inspection